   Construction of 60  MLD  STP & Sewer network - (under Hybrid annuity based PPP mode-Namami
                 Gange Programme)The project was completed in February 2024 (As per physical progress - MPR as of
                 March 2024)

              Â   Construction of 182 MLD Rehabilitation and up-gradation of Phase-I STP . The project was completed
                 in March 2024


              (As per physical progress - MPR as of March 2024) Treatment Capacity in the Basin:

              Time Period                                      No. of  Years         Capacity Created (MLD)
              Apr’ 1985 – Mar’ 2014                                 29                        1,221
              Under Namami Gange                                    10                        3110.5
              (2014 – ‘15 to Mar’ 2024)

































































              44.95 MLD STP in Etawah