Page 34 - Patrika 43-Jan-Mar-26-May-19-curve-file.cdr
P. 34
cost of Rs. 331.75 Crore 4.I&D and STP works at 5. I&D and STP works at
under, the Namami Gange Phusro, Jharkhand. Chakdah, West Bengal.
Programme. The major a)The project ‘I&D and STP a) The project ‘I&D and STP
components of the project works at Phusro, Jharkhand’ works at Chakdah, West
was sanctioned at an esti-
include: Bengal’ was sanctioned at an
mated cost of Rs. 61.05 Crore
I. Sewage Treatment Plant estimated cost of Rs. 121.66
under the Namami Gange
(STP) – 43 MLD (1 STP). Crore under the Namami
Programme. The major compo-
b) This STP is developed on Gange Programme. The major
nents of the project include:
Sequential Batch Reactor components of the project
I. Sewage Treatment Plant
(SBR) technology and has include:
(STP) – 14 MLD (2 STP).
been designed to treat the b) This STP is developed on i. Sewage Treatment Plant
(STP) – 15 MLD (1 STP).
wastewater to meet the Sequential Batch Reactor
b) This STP is developed on
stringent discharge standards (SBR) technology and has been
Sequential Batch Reactor
as prescribed by the Hon’ble designed to treat the
(SBR) technology and has been
National Green Tribunal. wastewater to meet the strin-
designed to treat the
c) The project has been gent discharge standards as wastewater to meet the
implemented on the DBOT prescribed by the Hon’ble
National Green Tribunal. stringent discharge standards
Model.
c) The project has been imple- as prescribed by the Hon’ble
d) The project will benet a
mented on the DBOT Model. National Green Tribunal.
city population of
d) The project will benet a city c) The project has been
approximately 14,00,000
population of approximately implemented on the DBOT
people by tapping their
90,000 people by tapping their Model.
generated sewage through the generated sewage through the d) The project will benet a city
Interception and Diversion Interception and Diversion population of approximately
components, thereby components, thereby improv- 1,34,000 people by tapping
improving the city's sanitation ing the city's sanitation status their generated sewage
status and avoiding discharge and avoiding discharge of through the Interception and
of untreated sewage to the untreated sewage to the River Diversion components,
River Ganga. Damodar. thereby improving the city's
sanitation status and avoiding
discharge of untreated sewage
to the River Ganga. In
addition, the following STPs
are partially commissioned in
Q4
43 MLD STP at Salori Prayagraj 10 MLD STP at Phusro 15 MLD STP at Chakdah
34