cost  of  Rs.  331.75  Crore  4.I&D  and  STP  works  at              5.  I&D  and  STP  works  at
             under,  the  Namami  Gange  Phusro, Jharkhand.                        Chakdah, West Bengal.
             Programme.        The     major    a)The  project  ‘I&D  and  STP     a)  The  project  ‘I&D  and  STP
             components  of  the  project       works  at  Phusro,  Jharkhand’     works  at  Chakdah,  West
                                                was  sanctioned  at  an  esti-
             include:                                                              Bengal’ was sanctioned at an
                                                mated cost of Rs. 61.05 Crore
             I.  Sewage  Treatment  Plant                                          estimated  cost  of  Rs.  121.66
                                                under  the  Namami  Gange
             (STP) –  43 MLD (1 STP).                                              Crore  under  the  Namami
                                                Programme. The major compo-
             b)  This  STP  is  developed  on                                      Gange Programme. The major
                                                nents of the project include:
             Sequential     Batch    Reactor                                       components  of  the  project
                                                I.  Sewage  Treatment  Plant
             (SBR)  technology  and  has                                           include:
                                                (STP) –  14 MLD (2 STP).
             been  designed  to  treat  the     b)  This  STP  is  developed  on   i.  Sewage  Treatment  Plant
                                                                                   (STP) –  15 MLD (1 STP).
             wastewater     to    meet    the   Sequential     Batch    Reactor
                                                                                   b)  This  STP  is  developed  on
             stringent discharge standards  (SBR) technology and has been
                                                                                   Sequential    Batch     Reactor
             as  prescribed  by  the  Hon’ble  designed      to     treat    the
                                                                                   (SBR) technology and has been
             National Green Tribunal.           wastewater to meet the strin-
                                                                                   designed     to     treat    the
             c)  The  project  has  been        gent  discharge  standards  as     wastewater     to   meet     the
             implemented  on  the  DBOT         prescribed  by  the  Hon’ble
                                                National Green Tribunal.           stringent discharge standards
             Model.
                                                c) The project has been imple-     as  prescribed  by  the  Hon’ble
             d)   The project will benet a
                                                mented on the DBOT Model.          National Green Tribunal.
             city       population         of
                                                d) The project will benet a city   c)  The  project  has  been
             approximately        14,00,000
                                                population  of  approximately      implemented  on  the  DBOT
             people    by    tapping    their
                                                90,000 people by tapping their     Model.
             generated sewage through the       generated sewage through the  d) The project will benet a city
             Interception  and  Diversion       Interception  and  Diversion  population  of  approximately
             components,             thereby  components,  thereby  improv-        1,34,000  people  by  tapping
             improving the city's sanitation  ing the city's sanitation status  their       generated       sewage
             status and avoiding discharge  and  avoiding  discharge  of  through  the  Interception  and
             of  untreated  sewage  to  the     untreated sewage to the River  Diversion             components,
             River Ganga.                       Damodar.                           thereby  improving  the  city's
                                                                                   sanitation status and avoiding
                                                                                   discharge of untreated sewage
                                                                                   to   the   River   Ganga.     In
                                                                                   addition,  the  following  STPs
                                                                                   are partially commissioned in
                                                                                   Q4





















             43 MLD STP at Salori Prayagraj         10 MLD STP at Phusro              15 MLD STP at Chakdah